Purnia Airport to Begin Air Services by June 2025.

by Editor
0 comment

Air services from Purnia Airport are poised to take off by June next year, marking a significant milestone for the region’s connectivity and economic development. The Airport Authority of India (AAI) has taken a decisive step forward by issuing a tender for the construction of an interim terminal building based on the porta cabin concept. This innovative approach is expected to accelerate the airport’s readiness for operations, ensuring that the region’s growing demand for air travel is met promptly.

The tender, released on Tuesday, outlines a strict timeline of four months for the completion of the terminal building. The project is estimated to cost ₹45.45 crore, encompassing not only the construction phase but also a comprehensive defect rectification period of 24 months and a maintenance contract spanning three years. This multi-pronged approach is aimed at ensuring both the quality and longevity of the interim terminal while providing immediate relief to travelers eager for better connectivity.

The decision to utilize the porta cabin concept reflects a pragmatic solution to address immediate infrastructure requirements. Porta cabins, known for their modular and prefabricated design, are cost-effective, quick to deploy, and customizable to meet functional needs. This model has been successfully implemented in various parts of the country where rapid infrastructure deployment is essential. By adopting this approach, AAI is ensuring that Purnia Airport is operational in the shortest possible time frame, while a more permanent infrastructure plan is envisioned for the long term.

Once operational, Purnia Airport is expected to play a transformative role in the region’s development. Improved air connectivity will not only reduce travel time for residents but also attract businesses and tourists, contributing to the socio-economic upliftment of the area. The airport’s strategic location makes it a vital addition to the national aviation network, potentially linking Purnia to key cities across the country.

The project’s estimated cost reflects the scale and ambition behind this endeavor. With a defect rectification period of two years and a three-year maintenance contract included in the plan, AAI is committed to delivering a facility that meets high operational standards. This comprehensive planning also underscores the authority’s dedication to ensuring long-term functionality and user satisfaction.

Local residents and businesses are hopeful that the introduction of air services will open up new opportunities for trade, investment, and employment in the region. For years, the absence of direct air connectivity has been a hurdle for Purnia, forcing residents to rely on distant airports or long road journeys. The upcoming launch of air services from Purnia Airport is set to alleviate these challenges, providing a much-needed boost to regional mobility and convenience.

The commencement of construction in the coming months will mark the beginning of a new era for Purnia, with air services expected to start as early as June 2025. As the interim terminal takes shape, the vision of Purnia becoming a significant hub in the regional aviation network is set to become a reality, bringing with it the promise of growth and progress.